The Ohio State University

Neil Avenue

NCS’ work on the Neil Avenue Improvements was completed in the Fall of 2002.

The project consisted of:

  • 1,942 sy 8″ Pavement
  • 1,750 lf 6 x 18 Curb
  • 10,840 sf 5.5″ Concrete Sidewalk
  • 288 lf 12 x 18 Curb
  • 9 ea Handicap Ramps
  • 2 ea Concrete Medians

Cannon Drive S-Curve

NCS’ work on Cannon Drive South Curve was completed in the Fall of 2004. NCS self performed the removal and replacement of all existing sidewalk, pavement, and curb.

The project consisted of:

  • 15,750 sf 10″ Reinforced Pavement
  • 1,440 lf 2′ Wide 10″ T Curb & Gutter
  • 1,950 sf 5.5″ Sidewalk

South Oval Underdrain

NCS’ work on South Oval was completed in the Fall of 2005.

The project consisted of:

  • Phase I: Install pipe, stone, & rough grade
  • Phase II: Fine grade, rock hound, hydroseed, fertilize, and mulch

Baker Hall 11th Avenue

NCS’ work on Baker Hall 11th Avenue was completed in the Fall of 2005.

The project consisted of:

  • 474 sf 4” walk

Bike Trail

NCS’ work on the OSU Bike Trail was completed in the Fall of 2006.

The project consisted of:

  • 3,657 sy Subgrade Compaction
  • 30 ea Linear Grading
  • 3 ea Bollards
  • 8 ea Guard Posts
  • 33 cy Rock Channel Protection
  • 6,620 sy Seeding and Mulching
  • 8.14 cy Concrete Masonry
  • 40 lf 12” conduit, type b
  • 80 lf 24” conduit, type b
  • 58 lf 36” conduit, type b
  • 40 lf 6’x3’ conduit, type a
  • 610 cy 304 aggregate base
  • 370 cy Asphalt
  • 252.05 cy #1 Aggregate Base
  • Clearing and grubbing, temporary soil erosion, traffic maintenance, and construction layout were also performed on this project.